换热站(热力站)施工组织设计施工方案
- 格式:doc
- 大小:72.00 KB
- 文档页数:12
**热力站
施工组织设计
编制:
审核:
批准:
********工程集团有限公司
年月日
目录
一、工程概况----------------------------------------
二、施工技术与方案----------------------------------
1,施工规范及验收依据·······································2,换热机组安装方案·········································3,泵类安装·················································4,水箱的制作与安装·········································5,管道及附件安装方案·······································6,阀门、压力仪表安装·······································7,配电柜安装···············································8,除锈防腐·················································9,试压·····················································10,保温····················································11,系统调试················································三、施工组织计划与措施------------------------------
1,开工前需要做好的施工准备工作·····························2,项目管理人员配置及劳动力计划·····························3,拟投入的机械、设备及进场计划
4,质量计划与保证措施·······································5,进度计划及保证措施·······································6,安全文明施工管理·········································
2015年天津市**热力有限公司**供热工程**热力站
施工组织设计
一、工程概况
本工程为2015年天津市**热力有限公司**供热工程**热力站,施工地点位于西青区中北镇,供热主体为澜湾广场和澜湾花园,分一期和二期工程两部分,工程内容包括设计安装全自动换热机组3套,一期2套换热机组,设计热负荷为Q6098kw,二期1套机组设计热负荷为Q480kw;管道安装包含螺旋焊接钢管ø325*7/50米,ø273*6/110米,ø219*6/10米,直缝焊接钢管DN150/140米,DN125/10米,DN100/100米,DN80~DN25/107米,管件安装包含阀门、弯头、变径等;设备系统其他安装包含循坏水泵2台,补水泵2台,除污器3台,2*2*1.5水箱1个等;以及设备相关电气、仪表系统的所有安装。
二、施工技术与方案
1,施工规范及验收依据
《板式换热器》GB/T16409
《城市热力网设计规范》CJJ34-2002
《工艺设备及管道绝热工程设计规范》GB50264-1997
《输送流体用无缝钢管》GB/T8163-1999
《现场设备、工业管道焊接工程施工及验收规范》GB50236-98
《工业金属管道工程施工及验收规范》GB50235-1997
《工业设备及管道绝热工程机验收规范》GBJ126-1989
《工业自动化仪表工程施工及验收规范》GB93-86
《室内热力管道支吊架》94R402
《压缩机、风机、泵安装工程施工及验收规范》GB50275-98
2,换热机组安装方案
(1)、换热机组到货验收、设备基础验收:
设备到货后的验收:对板换进行外观检查应做到如下标准:螺栓无松动、棱角无碰撞、板换进出口封闭严密、板换换热片排列整齐、胶垫无外露、板换型号与图纸要求符合、其他资料齐备(出厂合格证、技术参数等),换热片前后尺寸一致,无异常变形等。
设备吊运就位前的基础验收:根据图纸确定基础位置,测定标高,使用侧尺测定地脚螺栓孔的深度及长宽。基础表面清理干净,地脚螺栓孔内无积水杂物,基础外观无裂纹空洞等缺陷。为使二次灌浆层与基础能很好的结合,基础表面铲麻。
(2)、设备吊运及就位:
设备吊运通道及吊运方案根据现场实际情况而定,但需得到建设单位和监理单位现场管理人员的同意。机组吊上基础后,在机组四角用四台满足要求的千斤顶将机组提升,进行平面位置找正。待机组中心与基础中心线重合,放下机组。再进行第二台设备机组的就位。
(3)、找正找平:
设备就位后,先进行初找,每个地脚螺栓应有两组垫铁,垫靠位置应置于地脚螺栓受力部位,每组垫铁应放置整齐,其入深应超过地脚螺栓,每组垫铁数量不应超过3块,与基础面接触点均匀,外漏部分不得超过30mm,每组垫铁均匀受力垫铁块均压实、压紧。可用塞尺进行检查。设备正表面弹出中心线与基础纵向中心线垂直,使用磁力线坠测量正面、侧
面的板换垂直度,并通过垫铁块进行调整。地脚螺栓放置应自然下垂,铅垂度应小于1%,不贴住孔壁,螺栓底端不应碰孔底,其距离均不小于15mm ,地脚螺栓放置前应清除油污。螺母及垫圈与设备底座间完全接触。地脚螺栓浇灌后,将螺母手紧即可。灌浆宜采用细碎石砼凝土,其强度应比基础强度高一号,捣实时注意地脚螺栓不应倾斜。待砼达到强度的75%后方能进行紧固,随时测量板换垂直度并随时调整。达到规范要求后,紧固地脚螺栓,其螺栓应露出螺母3-4丝,并在丝头上涂抹黄油。设备找正工作完成后选优质彩条布进行遮护,防止意外损伤和各种污染。
3,泵类安装
(1)泵开箱验收
经与图纸核对无误,采用8 t吊车配合130车进行装运,吊装时应将钢丝绳提吊在包装箱底部,整体装车。途中捆绑紧固,注意滑动,摔倒。到现场后会同业主、监理进行开箱验收,主要检查以下内容:
外观:泵及泵座无裂纹,电机外壳无挤压变形,泵进出口法兰眼数量,水线清晰,泵口封堵完好。
资料:说明书、产品合格证书、技术参数数据完整。
配件:放气阀、地脚螺栓、泵体螺栓有无缺陷、出厂时密封部位有无拆卸现象、电机吊耳是否牢固。
盘车:检查泵体进出口有无杂物并手动进行盘车。盘车应灵活,无卡阻、无异常声音。
检查合格后填写开箱验收记录,对有问题的泵,恢复外包装,等候业主、监理的处理意见。
(2)水泵安装
基础划线并验收合格后进行泵的安装,安装前必须进行设备的检修工作(制造厂有特殊要求的除外),并按照规范要求做设备的保养,作好检修记录。
必须在甲方、监理和施工单位三方在场的情况下进行风附机和泵的试运工作,施工人员要认真做好试运纪录,并办理验收签证。
※泵的安装误差
纵横中心线2mm
中心标高2mm
※安装前应对水泵的主要安装尺寸与设计图纸相比较,吻合;
※水泵试运转
※电机的转向应为正转;
※检查地脚螺栓有无松动;
※检查仪器仪表工作是否正常;
※泵运行前,应先打开水泵上端防气阀,水泵内是否有空气,一定要放掉;
※泵在运转过程中不得有异常声音和转子与定子之间有摩擦等情况;
※安全保护和电控装置和仪表必须工作正常,使用均应灵敏;
※水泵的试运转时间应大于2小时以上。
4,水箱的制作与安装
检查→钢板、型钢调校→按图划线、切割、下料→焊接部位加工(坡口)打磨→连接法兰组件、加工、钻孔→箱体拼组、对接、焊接(圆形体卷制、对接、焊接)→法兰与道体组装、焊接→外观尺寸检查→焊缝检查→产品整体验收→吊装→人孔、接口及附件安装※根据图纸外型尺寸,检查平台。平台应稳定、可靠,表面清洁。